Migration of Customizing ProjectsLocate this document in the navigation structure

Procedure

To migrate customizing projects from older systems into the current system:

  1. Choose Start of the navigation path System Next navigation step Services Next navigation step Reporting End of the navigation path.

  2. Enter the program name MIGRATE_PROJECT_NEW.

  3. Choose Start of the navigation path Program Next navigation step Execute End of the navigation path.

  4. Enter the project number of the old Customizing project which you want to copy into the current system.

  5. Choose Start of the navigation path Program Next navigation step Execute End of the navigation path.

    The application component hierarchy is displayed in a window.

  6. Choose the application component for the new customizing project.

  7. Choose Continue.

    The project IMG for the new customizing project is generated.

Result

The complete contents of a customizing project from a Release 3.0, 3.1, 4.0 or 4.5 R/3 System are copied into the current release.