Planning SequenceLocate this document in the navigation structure

Use

Planning sequences are used in BW-Integrated Planning to group planning functions. They allow you to save groups of planning functions in a sorted sequence and execute groups of planning functions sequentially.

Integration

Planning sequences can be edited, saved and tested in Planning Modeler.

They can be included in a process chain as a step. They can also be linked to a variant of variable values.

Features

A planning sequence can be made up of one or more steps. There are various types of steps:

Type

Description

Planning function

Based on an aggregation level, the system saves a planning function and a filter with which the planning function is executed.

Input template

You can embed input templates in the sequence to test planning functions. Input templates are defined by an aggregation level and a filter.

If a planning sequence is executed in its entirety, the embedded input templates are ignored.

Activities

Testing a Planning Sequence in Planning Modeler

In Planning Modeler, choose Execute to test entire planning sequences or execute planning sequences step by step. More information: Editing a Planning Sequence.

Executing a Planning Sequence in a Process Chain

You can embed a planning sequence in a process chain using process type Execute Planning Sequence. The planning sequence can be linked with a stored variant for variable values. More information: Scheduling Planning Sequences in Process Chains. An example is provided under

Planning Sequence for Bottom-Up Planning