Assigning Demands to Other Resource Planning Nodes 
As a resource planner, you can reassign a demand to a different resource planning node in the resource planning board. This function is not available for CRM service orders.
You have defined the Customizing settings under .
To assign an order operation to another work center, you can assign another resource planning node on the details screen for the demand. The system then transfers this change to the order operation when you choose save.
In the same way, you can assign another resource planner for network activities by assigning another resource planning node on the demand detail screen. Once you have saved the change, it is also displayed in the network activity.
To start the “Reassign” function from the resource search in the planning board, choose Reassign RP node from the context menu for the resource in the result list. The default value for the new resource planning node is the resource planning node of the selected resource in this case.
You can either reassign the entire demand to another resource planning nodes or split parts of the demand and assign these to other resource planning nodes.