Process Variant Overview for Resource Planner Process 
You have configured the necessary settings in Customizing for SAP Multiresource Scheduling under .
In the cProject, you have assigned an organizational unit that is to be used for the resource planner process on the tab page .
In this process, the demand is assigned immediately to the resource planner of the organizational unit from the project.
Automatic Posting
The resource planner finds a suitable resource and creates assignments for it.
The system automatically hard books the resource for this assignment, meaning that the softbooking step is omitted.
Manual Confirmation
The resource planner finds a suitable resource and proposes it to the project manager. The proposal is displayed on the MRS tab page of the role in the cProject.
The project manager decides whether to select or reject the resource. However, he or she can also choose to simply reserve it.
Until this point, the resource is handled as a softbooking.
The resource planner can hard book or reserve the resource selected or reserved by the project manager in the planning board. If the resource planner hard books the resource, the softbooking is converted to a hardbooking and the resource is assigned the status Allocated.
Automatic Selection
The resource planner (resource manager) searches for a suitable resource and can accept it.
It is then proposed to the requester (project manager) in the cProject.
The project manager (requester) can then select or reject the proposed resource.
The resource manager (resource planner) can hard book the resources selected in the planning board for the assignment.