Creating a Production Process for a Cost Object Hierarchy You want to create a
cost object hierarchy
for the Controlling level
Material / Plant /
Production Process
.
The production process that you want to assign has not been created.
A production process may already have been created for one of the following reasons:
You have created a mixed cost estimate for the material.
You have already created a product cost collector for the material.
You are using the application component
Actual Costing / Material Ledger
.
Choose .
The screen
Display Production Processes
appears.
Enter the following data:
Material
Plant. Note that the plant of the cost object node is the same as the planning plant in the manufacturing order.
Choose
The screen
Assign Controlling Level for Material
appears.
Choose a Controlling level by positioning the cursor.
Choose
Confirm
.
The screen
Create Production Process
appears.
Enter the following data:
The characteristics for the Controlling level (such as the production version if the Controlling level is
Production Version
)
A short text
Choose
Confirm
.
Save the production process.
The system has created a production process for the material.
The production process was created in accordance with the Controlling level you selected. This Controlling level is valid for this plant material and can be changed under certain conditions. See also: Editing the Controlling Level