The assigned value for projects is calculated from:
Actual costs of WBS element carrying budget
Statistical actual costs of WBS element carrying budget
Actual costs of subordinate WBS elements if these do not carry budget
Statistical actual costs of subordinate WBS elements if these do not carry budget
Commitments of WBS element carrying budget
Commitments of subordinate WBS elements if these do not carry budget
Maximum of plan and actual costs + commitments from assigned networks or orders
( )
For more information, see the Implementation Guide (IMG) under Project System Õ Costs Õ Planned Costs Õ Define Order Value Updating for Orders for Projects .
Debit from settlement to WBS element
Credit from settlement to budget-controlled object (internal order, WBS element)
Caution
Not used for calculation of the assigned value:
Actual costs with a cost element defined in Customizing for availability control as an exempt cost element
For more information, see the implementation guide (IMG) under
.Actual costs that resulted from a business transaction that does not belong to the valid business transaction groups of availability control
( )
This can happen if you have not defined ++ as a business transaction group in Customizing for tolerance limits .
For more information, see the Implementation Guide (IMG) under
.Credits from settlement to an object that is not budget-controlled (for example, cost center)
Revenues