 Creating and Marking an Order BOM Cost Estimate Locate this document in the navigation structure

Prerequisites

Define the costing variant in Customizing for Product Cost Controlling . You can specify in the costing variant whether you want the itemization to be saved.

Procedure

  1. Choose   Accounting   Controlling   Product Cost Controlling   Cost Object Controlling   Product Cost by Sales Order   Costing   Order BOM   Create   .

  2. The screen Create Cost Estimate for Order BOM appears.

  3. Enter the following data:

  • Number of the SD document and the item

  • Also enter the costing variant, material, plant, and costing lot size (if applicable)

Note Note

The costing variant, material, plant, and costing lot size can also be:

- Entered manually

- Transferred from the sales order item This data is transferred from the sales order item if the data has been entered in the sales order item and you do not enter any data manually here.

End of the note.
  1. Choose Enter .

The system transfers the control parameters (costing dates and transfer control) from the costing variant, and costs the order BOM.

Result

The system always updates a cost component split for the order BOM cost estimate. When you save the cost estimate, you can choose whether you also want to save the itemization.

You can display the following on an order BOM cost estimate:

  • A list of the costed materials

  • A list of the costing levels

The costing level controls the sequence in which the materials are costed. The costing level is issued internally by the system and is inverse to the low-level code. The costing level enables cost rollup over more than one manufacturing level.

  • Another cost component view

If you want to calculate the standard price for the sales order material on the basis of the order BOM cost estimate, mark the order BOM cost estimate. Do this by choosing   Extras   Mark   . The system assigns the status VO (marked) to the cost estimate.

To view the cost estimate at a later time, access the Product Cost by Sales Order menu and choose   Master Data/Planning   Cost Estimate for Order BOM   Display   and enter the required data. Then choose Enter .