Show TOC

Procedure documentationDisplaying Pegged Requirements Locate this document in the navigation structure

 

In the planning table, you can display the pegged requirements of a production quantity.

Procedure

  1. Double-click the production quantity.

    If the production quantity only consists of one planned order, a dialog box appears displaying the detailed data for this order.

    If the production quantity consists of several planned orders, the system first displays the Planned Orders Details screen which lists all the planned orders for this quantity. Double-click the planned order for which you want to see the pegged requirements. A dialog box appears displaying the detailed data for this order.

  2. Choose Pegged requirements.

    The system branches to the Pegged Requirements screen where you can see all the pegged requirements.