Show TOC

 Invoke Delayed Replenishment Elements Locate this document in the navigation structure

Use

With this evaluation, you can determine for empty kanbans whether or not the receipt of a replenishment is delayed.

Note Note

You can also define report SAPMMPKAL as a background job and have it run periodically.

End of the note.

Procedure

  1. Choose   Logistics   Production   Kanban   Evaluations   Delayed Replenishment Elements   .

    The selection screen for the replenishment elements appears.

  2. Enter the plant for which the delayed replenishment elements are to be determined.

  3. Check the delivery date.

    In the standard system, the default delivery date is the current date.

  4. Select the Send Alerts indicator if an alert is to be sent to the Alert Monitor for the delayed replenishment elements.

    You have activated the alerts for the replenishment strategy in Customizing for this purpose.

    Because the alerts are generated from error messages, you must also ensure that the error messages for the alerts are not switched off (see Activation of Kanban Alerts ).The relevant Customizing activity is   Production   Kanban   Status   Kanban Alerts: Switch Off Error Message   .

    You have previously activated the alerts in the replenishment strategy. You have not switched off the alerts for the relevant error message.

  5. Define the desired criteria for selection. As with every report, you can save these criteria as a variant.

  6. Choose Execute .

  7. The delayed replenishment elements are displayed in accordance with the selection conditions.

    Note Note

    The Business Add-In BAdI_GUI_ALV_GRID_EXT in enhancement ES_GUI_ALV_EXT enables you to adjust the output table on a customer-specific basis.

    Notes on the implementation of the BAdI are available in Customizing under   Production   Kanban   Business Add-Ins   BAdI: Adjust Output Table for Delayed Replenishment Elements.  

    End of the note.