Show TOC

 Displaying Pegged Capacity Locate this document in the navigation structure

In the planning table, you can display the source of the capacity requirements.

Prerequisites

You must have selected Capacity planning on the initial screen.

Procedure

  1. Double-click the capacity requirement or load for which you want to see the pegged capacities. The system displays the dialog box entitled List of MRP Elements .

  2. Double-click the MRP element to choose the pegged capacity you want to display. The system displays the dialog box Prod.Quantities Detailed Data.

  3. Choose Pegged reqmts . The system displays the Pegged Requirements screen.