 Display Actual Capacity Requirements Locate this document in the navigation structure

Use

In the extended evaluation you can display actual capacity requirements as well as planned capacity requirements or remaining capacity requirements.

The system calculates the actual capacity requirements during confirmation from the confirmed activity or - using the formulas from the work center - from the confirmed quantity.

Prerequisites

Capacity in the work center

If you want to display actual capacity requirements in the extended evaluation you must specify the following in the screen Capacity overview in the work center for the capacity categories:

  • That the actual capacity requirements are determined during confirmation

  • How the actual capacity requirements are calculated

  • So that the system can calculated actual capacity requirements from the confirmed quantity you must have specified formulas to calculate the capacity requirements for the operation segments or for the internally processed operations.

  • So that the system can treat the confirmed work as actual capacity requirements you must specify in the work center which work is assigned to which operation segment or to which internally processed operation. You specify the appropriate standard value parameters for every actual capacity requirement for an operation segment or for the internally processed operation.

Customizing for the capacity category

If you do not set the indicator NoActValue in Customizing for the capacity category then on confirming an individual capacity actual capacity requirements are generated for the individual capacity and for the main capacity category to which the individual capacity is assigned. If you set the indicator NoActValue only actual capacity requirements are generated for the individual capacity.

Confirmation for operation

If the system is to calculate actual capacity requirements from confirmed activities you must specify the confirmed activities during confirmation using a unit with a time dimension.

Note Note

When confirming the order the system does not calculate actual capacity requirements.

End of the note.

Customizing for capacity leveling and the extended evaluation

  • In the selection profile you specify which capacity requirements categories you can display in the extended evaluation (planned-, remaining- or actual capacity requirements). If you do not select a capacity requirement type you can only display remaining capacity requirements in the extended evaluation.

  • In the list versions for the detailed capacity list and the standard overview you specify which data the system displays on calling up the extended evaluation, for example actual capacity requirements. In the extended evaluation you can change the field selection at any time.

Note Note

An overall profile for the extended evaluation that displays the actual capacity requirements is the profile SAPSFCGO23.

End of the note.

Features

When carrying out a confirmation you can also specify the dates between which you have processed the quantity or carried out the activity confirmed (start processing, finish processing). In the extended evaluation the system distributes the actual capacity requirements using the distribution key over the periods between these dates.