If you use statistical key figures, activity quantities, cost elements or prices in dependency planning that you did not plan manually or that you copied, the system does not automatically revalue your dependency planning.
You should revalue your planning manually if you:
Imported statistical key figures or activity quantities into the system using the external data interface.
Calculated statistical key figure quantities using formula planning
Transferred statistical key figure quantities from the LIS (Logistics Information System) to cost center planning.
Transferred activity quantities from PP to cost center planning.
Calculated activity quantities using indirect activity allocation
Calculates prices for activity types using price calculation
Note
If you make the following changes to planning, the system automatically revaluates dependency planning after each change:
Changes to manually-planned values
Changes to planned values due to plan reconciliation
Changes to copied plan values for cost elements
Note
The system does not automatically revalue copied activity quantities and key figure quantities.
To revaluate resources:
Choose
.Specify for which cost centers your dependency planning is to be revaluated as follows:
Single cost centers
A cost center group
All cost centers
A selection variant that you define yourself
Enter a name for a selection variant.
Choose Create or Change (depending on whether you want to create a new selection variant or change an existing one).
Specify which data is to be revalued.
Save your selection variant .
Maintain the following fields:
Version
From period
To period
Fiscal year
Choose Execute .
Result
The system updates the revalued planned costs and the revalued planned consumption. You can check the results on the overview screen and on the period screen for planning.