To set the replenishment strategies for KANBAN, proceed as follows:
In Customizing for KANBAN choose Replenishment strategies .
Select which replenishment strategy you want to maintain:
In-house production
External procurement
Stock transfer
To create new strategies, select
Enter the corresponding parameters which control the replenishment strategies.
The parameters that you enter vary according to the type of replenishment. If, for example, you use run schedule quantities with MRP with KANBAN in-house production, then as well as the standard parameters such as control type and goods receipt movement type you have to maintain the reduction of planned orders, the reduction period and the creation of planned orders on cancellation.