In the budget profile, you define all values required for the budgeting process.
To do so, in Customizing:
For projects, choose Project System Õ Costs Õ Budget Õ Maintain Budget Profile .
For internal orders, choose Controlling Õ Internal Orders Õ Budgeting and Availability Control Õ Maintain Budget Profile .
For more information, see Basic Settings for Availability Control in Budget Profile .
The tolerance limits for the checks during activity control are defined for each transaction group of a budget profile.
To do so, in Customizing:
For internal orders, choose
For projects, choose Project System Õ Costs Õ Budget Õ Define Tolerance Limits .
For more information, see Specifying Tolerance Limits .
Exempt cost elements are those which are not included during availability control (such as, interest or credits for activities that were provided in a joint venture by one project for a partner project).
To do so, in Customizing:
For projects, choose Project System Õ Costs Õ Budget Õ Specify Exempt Cost Elements .
For internal orders, choose