The table parameter, an internal table, is dependent on the business transaction for which you want to transfer the external data. It contains the data itself, and is based on the standard SAP system table structure, which is dependent on the data being transferred (VRGNG parameter). The SAP system uses four different table structures for the transfer of planning data.
For costs
Periodic |
RKU01JA |
Cumulated |
RKU01G |
For quantities
Periodic |
RKU02JA |
Cumulated |
RKU02G |
Example
The name of the table used by a function module contains the name of the structure and the letter ' I' before it.
Structure: RKU01JA
Table name: I RKU01JA
These table structures contain many fields which are not required for transferring the external data from different planning areas. The structures are designed to transfer data from other business transactions at a later date.
Fields already filled in the structure are replaced by the transferred values.
The table below provides an overview of the function modules to be called up, with their corresponding table structures.
Function Modules and Table Structures
Function Module |
Table Structure |
K_COSTS_PLAN_INTERFACE_PERIOD |
RKU01JA |
K_COSTS_PLAN_INTERFACE_TOTAL |
RKU01G |
K_RKP6_INTERFACE_PERIOD |
RKU01JA |
K_RKP6_INTERFACE_TOTAL |
RKU01G |
K_ACT_PLAN_INTERFACE_PERIOD |
RKU02JA |
K_ACT_PLAN_INTERFACE_TOTAL |
RKU02G |
K_RATIO_PLAN_INTERFACE_PERIOD |
RKU02JA |
K_RATIO_PLAN_INTERFACE_TOTAL |
RKU02G |
K_ACT_INPUT_INTERFACE_PERIOD |
RKU01JA |
K_ACT_INPUT_INTERFACE_TOTAL |
RKU01G |
Below is a list of sample fields to be filled in the RKU01JA or RKU01G structure for transferring primary cost planning data that is activity-independent (business transaction RKP1).
Cost center, order number, or WBS element
Cost Element
Currency is either transaction currency, object currency, or controlling area currency. Only one currency type may be filled, and this must be indicated in IRKU01_CUR. If you use the transaction currency, then ensure that you make an entry in theTWAER field.
Total quantity
The GJAHR, KOKRS parameters and so on, no longer need to be transferred.
You can also make entries in more fields, such as:
Unit of measure
Record quantities indicator
One object type may be transferred for each function callup. Primary cost planning (activity-independent) on cost centers and orders, therefore, requires two separate callups.
For activity input planning for sender business processes, the P_PRZNR field must contain the key of the business process.
For order cost planning for sender business processes, the P_PRZNR field must contain the key of the business process.