 Planning Costs with the Planning Layout for Activity Type Planning Locate this document in the navigation structure

You can plan costs for general cost objects that have a periodic time base and whose cost object category allows planning as follows:

  1. Choose   Accounting   Controlling   Product Cost Controlling   Cost Object Controlling   Intangible Goods and Services   Planning   Cost Object - Periodic   Set Planner Profile   .

  2. The dialog box Set Planner Profile appears.

  3. Enter the desired planner profile (SAP101 or SAP102).

  4. First choose User master record and thenENTER .

  5. Choose   Planning   Periodic Planning Cost Object   Cost/Activity/Process Inputs   Change   .  

  6. This screen appears: Periodic Cost Object Planning Cost Elements/Activity Input Change: Initial Screen

    Enter data as required.

    ChooseENTER and then Overview screen .

    The screen Periodic Cost Object Planning Cost Elements/Activity Input Change: Overview Screen appears. The planning layout determines what cells can be entered or changed.

  7. Enter the fixed and variable quantities or the fixed and variable costs.

  8. ChooseENTER . The system calculates the planned costs for your general cost object.

  9. Save the cost estimate.

  10. Press Period screen to see the planned costs and the planned consumption for each period.

Note Note

You cannot plan overhead for general cost objects that have a periodic time base. However, it is still possible to distribute overhead costs to different general cost objects that have a periodic time base by using statistical key figures. The statistical key figures then serve as equivalences.

End of the note.