 Carrying Out the Activity Confirmation Locate this document in the navigation structure

Use

If more or fewer activities have actually gone into the production of a material than posted, you can use this function to subsequently post the excess or shortfall.

It may be necessary to post activity excesses or shortfalls if a difference arises after the posting of target (planned) and actual activities, which you have to balance off.

Procedure

  1. Starting from the initial screen of the confirmation, choose Activity Confirmation.

    The system displays the screen for entering activities.

  2. Enter a plant and the material for which you want to enter activities. If necessary, restrict your selection further.

  3. Enter “0” in the Reference Quantity field.

    In this way, you can differentiate between the posting of a difference and the posting of a total activity. When posting a total activity, enter the corresponding reference quantity here.

  4. Choose Continue .

    The system offers you the relevant operations for which you can post a difference.

  5. Choose an operation, then click Continue.

  6. Now enter the activity excesses or shortfalls and save.