 Carry Out Component Confirmation Locate this document in the navigation structure

Use

You can use the component confirmation to confirm the production of component scrap or the excess consumption of components in Repetitive Manufacturing.

A separate movement type is provided for the scrap confirmation, so that you can also define a separate cost element in Controlling. In Controlling, however, the scrap posted in this way is interpreted as excess consumption.

Procedure

  1. On the Repetitive Manufacturing Confirmation screen, choose Component Confirmation.

  2. Enter the plant and (in the Material field) the assembly for whose components you wish to post the goods issue. If necessary, specify the selection criteria according to which the BOM is to be exploded.

  3. If you want to enter the components manually, choose No BOM Explosion. Then you can enter the scrap quantities individually via Process Component List.

    If you want to have the system propose the components via the BOM, choose Propose Components Acc. to BOM. It is now possible to propose a reference quantity on the basis of which the BOM is exploded. If you do not propose a reference quantity, the system posts the planned quantities.

  4. If you want to post the component withdrawals for a certain reporting point only, select reporting point confirmation and enter the reporting point for which you wish to confirm.

    If you want to enter goods issues for operations that take place after the last reporting point in the routing, choose Comps After Last RP.

  5. If you enter a reference quantity, the system explodes the BOM on the basis of the quantity specified and automatically calculates the component quantity.

    Note Note

    If you do not enter a reference quantity, you must enter the scrap quantity manually on the following screen.

    In this way, you can post scrap for certain components. This is necessary if it is not the entire assembly that was scrapped, but only a constituent part, which was then replaced.

    End of the note.

    Choose Execute .

Result

The system posts the scrap and confirms the posting with an appropriate message.