The PRTs must have a master record in the system. According to the PRT category the following conditions have to be met additionally:
Materials, equipment and documents must be released, using their status, as production resources/tools.
Production resources/tools with a PRT master record (misc.) must be released in their status for use in resource planning.
PRTs with material masters, PRT masters or equipment masters must be intended for use in routing in their task list usage.
In the operation overview of the routing select the operation you want to assign PRTs to.
Choose
.– If you have already assigned PRTs to this operation the PRT overview for the operation appears.
In this case choose
and the category of the PRT you want to assign.– If no PRTs have yet been assigned the dialog box for PRT with category Material appears.
If you want to assign a PRT with a different category, choose the corresponding function key.
Enter the PRT as well as the item number and the basic data for PRT assignment and choose Continue .
If you want to assign more PRTs, choose
and the required PRT category. Continue as in step 3.After you have finished assigning PRTs, choose Back .
Select the assigned PRTs on the PRT overview and enter additional data about the assignments as required.
To enter default values, choose
To enter usage dates, choose
To enter a long text, choose
.