Show TOC

 Prerequisites Locate this document in the navigation structure

The following prerequisites must be met if you want to use the interface:

  • Valid bill of material

  • Valid routing

  • Valid settlement profile (Customizing:   Production Orders   Master Data   Orders)  

  • The production version, if used, must be valid for the time and lot size specified

  • Material availability: the material must be available in sufficient quantity or the indicator for the material availability check cannot be set for the status created or released (Customizing   Production Orders   Operations   Availability Check   Check Control).  

  • If the production order is to be costed, activity types and activity prices must be maintained in the work center or cost center