 Carrying Out Material Identification Locate this document in the navigation structure

Start Quantity Check

  1. From the PI sheet, call up the start quantity check.

The Material Identification: Start Quantity Check dialog box appears.

Depending on how it was defined in the master recipe, the components are displayed from the material list of the process order.

  1. Enter the material to be identified and, if possible, the batch.

  • If the material belongs to the process order, this is confirmed with a green checkmark.

  • If the material does not belong to the process order, an error message appears.

  1. To complete the start quantity check, choose Save .

  • If a partial quantity could be identified from each component of the process order, this is confirmed in the PI sheet.

The identification of the materials is saved and the identified materials are marked with a green dot in the start quantity check.

  • If not all of the components of the process order could be identified, an error comment appears in the PI sheet. In this case, the start quantity check is not considered to be executed.

Component Check

  1. From the PI sheet, call up the component check.

The Material Identification: Component Check dialog box appears.

Depending on how it was defined in the master recipe, the components are displayed from the material list of the process order.

  1. Enter the material to be identified and, if possible, the batch.

  • If the material belongs to the process order, this is confirmed with a green checkmark.

  • If the material does not belong to the process order, an error message appears.

  1. To complete the component check, choose Save .

This results in the following:

  • Batch splits that were carried out are transferred to the material list of the process order

  • The identified materials are entered in the batch record.