 Changing Material Prices Locate this document in the navigation structure

Prerequisites

If the material ledger is active , the material prices of materials whose price determination indicator is set to 3 can only be changed at the beginning of the period before all price-relevant transactions.

If the material ledger is not active, you can change the material prices at any time.

Procedure

  1. Choose   Logistics   Materials Management   Valuation   Material Price Change   Change Material Prices  

    or

    Choose   Accounting   Controlling   Product Cost Controlling   Actual Costing/Material Ledger   Material Ledger   Set Prices   Change Material Prices  

  2. Enter data as required.

  3. An overview screen appears.

  4. Fill in the fields in the overview screen.

  5. Choose Save .

Result

Inventory is revaluated with all price controls, including valuation with standard price and valuation with periodic unit price.