 Initial Phase of Mass Replacement of Work Centers Locate this document in the navigation structure

Prerequisites

You can carry out mass replacement of work centers

  • In the Work centers area menu

  • In the Routings area menu.

The rest of this topic only describes the start of mass replacement. For more information about the mass replacement of work centers in routings, see the SAP Library Routings (PP-BD-RTG), Mass Changes and Where-Used Lists.

Procedure

Starting from theWork centersarea menu

In the Work centers area menu choose   Work center   Replace.  

The Replace Work Center : Selection screen appears.

Starting from theRoutingsarea menu

In the   Routingsarea menu choose Extras   Mass Replace   Work centers.  

The Replace Work Center : Selection screen appears.