 Defining the Planning Segment Locate this document in the navigation structure

Prerequisites

You must create a line hierarchy and insert a sort buffer between the line segments.

Procedure

  1. Starting from the planning table choose   Sequencing   Select line segments.  

  2. The system displays the graphic display of the line hierarchy.

  3. To reset the current planning segment, select it and choose   Edit   Planning segment   Deselect   .

  4. Click on the new line segment to be defined as the planning segment and choose   Edit   Planning segment   Define   .

  5. Choose Back .

Result

The system uses the line segment you defined as the planning segment for scheduling in the sequence schedule.