Show TOC

 Changing the Planned Orders Locate this document in the navigation structure

Use

You use this function to change the detailed data of a planned order in the sequence schedule. For example, you can change the order quantity or the basic dates. You can also delete planned orders from the sequence schedule.

Integration

In the sequence schedule, the system initially only displays the detailed data significant for sequencing. From this display, you can go to the planned order to display or change the header data, for example.

Features

  • The overview displays the order data and dates of the planned order. If you use sort buffers to split the production line into buffered sections, the list of dates displays the dates (date records) for every buffered section.

  • The overview displays the key and the description of the material.

  • The overview displays the total processing time and the lead time.

  • The overview displays information on the material availability check.

Activities

Starting from the sequence schedule, select a planned order and choose   Goto   Order   Display, Change   or Delete .