Show TOC

 Creating a PRT with a PRT Master Record (Miscellaneous) Locate this document in the navigation structure

  1. In the SAP menu choose   Logistics   Production   Master data   Prod.resources/tools   and then   Prod.resources/tools   PRT master (misc.)   Create   .

  2. Enter the relevant data on the initial screen and choose Enter .

  3. If you have entered a source to copy from on the initial screen, select the data to be copied now, and choose Continue .

  4. Enter the relevant data on the Basic Data screen

  5. Choose   Goto   Defaults   and enter default values for the assignment of the production resource/tool (PRT) to operations.

    In case you want to take particular properties of the PRT into account in the formulas for total quantity and usage value, define the formulas as formula constants for the PRT. To do this, choose   Extras   Formula constants.  

  6. If required, enter additional test for the PRT.

    –To create language dependent short texts, choose   Extras   Short text.  

    –To create long texts, choose   Extras   Long text..  

  7. Save the production resource/tool.