Show TOC

 Deleting Operations with Inspection Characteristics Locate this document in the navigation structure

Use

If an inspection characteristic has been assigned to an operation (system status ICHA), you can delete the operation if the following requirements have been met:

  • The inspection characteristic is a "planned" inspection characteristic

  • QM data (status QMDA) has not yet been recorded for the operation

Procedure

  1. Delete the inspection lot assigned to the production order.

  1. Delete the operation in question.

  2. Regenerate the inspection lot

This will ensure that the inspection characteristics of the remaining operations remain in the production order.

Note Note

If you delete an operation that has already been released, the system activates the system status DLFL for the operation, but leaves the operation in the operation overview.

End of the note.