 Example for Sequencing Locate this document in the navigation structure

 ( )

In this example, the duration of the dispatching period is one day. The system determines all the planned orders whose order start dates lie on this particular day and assigns them to this day. Then the system plans the sequence of these planned orders using the first-in-first-out process.

 ( )

In this example, the duration of the dispatching period is two days. Therefore, for sequencing, the system determines all planned orders whose order start date lies within 2 days and dispatches these planned orders using the FIFO process. Here, the orders are dispatched as early as possible. If there is sufficient time to dispatch all the planned orders to the first day, the second day is left free.