You have already assigned a material component to an operation as a to-be-provided component
You now want to assign another component to the same operation, but this component is not to-be-provided.
In the operation overview choose
The Material Component Overview screen appears
Select the BOM item that you want to provide and choose
.The New Assignment screen appears.
Enter the operation that the component is to be provided for and choose Continue .
You return to the Material Component Overview screen.
Choose
The item overview for the BOM appears
The Item: Status/Long text screen appears.
Enter L in the Mat. provision ind . field and choose Back twice.
You return to the Material Component Overview screen
Save your routing.