 Converting Production Campaigns Locate this document in the navigation structure

Use

To be able to process planned orders, you must first convert them to process orders.

Procedure

  1. On the Create Production Campaign: Overview screen, select the desired planned orders and choose Environment -> Convert to proc. ord.

  2. A dialog box containing data on the order type appears.

  3. Enter the order type for the process orders to be produced and choose Continue .

  4. The planned orders selected are now converted to process orders.

  5. Save the campaign.