  Confirmation of Process and Production Orders Locate this document in the navigation structure

Use

You can use the mass processing function (transaction COHV) to enter confirmations against production orders.

In mass processing for process orders (transaction COHVPI), you can enter confirmations againstprocess orders. You enter confirmations against process orders in the same way as you enter them against production orders.

Integration

In mass processing, you can also enter confirmations against planned orders from repetitive manufacturing. Further information on entering confirmations against planned orders is available unter Mass Processing Functions for Planned Orders

Prerequisites

  • To enter confirmations against production orders, you must have previously set the Production Orders indicator on the initial screen for the mass processing of production orders.

  • To enter confirmations against process orders, you must have previously set the Process Orders indicator on the initial screen for the mass processing of process orders.

Features

List Types and Layouts

The following table provides an overview of the most important list types and layouts available for confirmations relating to production and process orders.

List type

Layout

Order headers

Standard layout confirmation 000000000003

Operations

Standard layout confirmation 000000000005

Production list

This list type contains information from the header data of the selected production and planned orders plus certain MRP information such as:

  • Target quantity

  • Yield already confirmed

  • Range-of-coverage data

  • Available quantity

Standard layout confirmation 000000000002

Confirmation Type

The following confirmation types are available for production and process orders:

  • Enter confirmation against order

    If you work with the Function with Dialogoption, you branch to the individual entry of order confirmations. You then enter confirmations for the selected objects one after the other. If you have chosen the options Execute function immediatelyor Execute function in background, the confirmations are carried out with the expected values, provided this is set up in Customizing (Customizing for Shop Floor Control , under   Operations   Confirmations   Confirmation Parameters Collective Entry/Fast Entry   ).

  • Enter time ticket

    If you work with the Function with Dialog option, you branch to the collective entry function for time tickets. You then enter confirmations for the selected objects one after the other. If you have chosen the options Execute function immediately or Execute function in background , the confirmations are carried out with the expected values, provided this is set up in Customizing (Customizing for Shop Floor Control , under Operations -> Confirmations -> Confirmation Parameters Collective Entry/Fast Entry ).

  • Enter time event

    Time events can only be executed with the Function with Dialog option (see Entering a Confirmation for a Time Event). You enter confirmations for the selected objects one after the other.

Entry in Error Table

If you have chosen the options Execute Function Immediately or Execute Function in Background , it is not possible to check for errors in dialog. In this case, you can decide whether unprocessed confirmations are to be made available available in confirmation postprocessing : You can choose between the following options:

  • No entry in error table

  • No entry in error table in case of lock situations

  • Enter all unprocessed confirmations in error table

Switch Confirmation Fields to 'Ready to Accept Input'

For the list types order headers and production lists , you can specify in the Switch Confirmation Fields to Changeable field on the Mass Processing tab page that certain fields on the confirmation list are to be ready to accept input. This is only possible in connection with the confirmation type Enter Confirmation for Order . The Switch Confirmation Fields to Changeable field is also offered in the case of the list type Operations , but only in connection with the confirmation type Enter Time Ticket . If you set this indicator, you can enter the the real actual quantities. This is possible for the following fields:

  • Yield

  • Scrap

  • Rework

  • Unit of measure

  • Reason for variance

In addition, you can use the Default Values field to specify whether or not the changeable quantity fields are to be prepopulated with default values when the list is displayed.

You can choose between the following options:

  • No default values

    The system does not suggest/preset any data.

  • Suggest planned values

    The system suggests the quantity still to be confirmed according to the planning. In addition, the automatically determined confirmation type is suggested.

  • Suggest fixed values

    If you choose this option, the system shows the fields Confirmation Type, Yield, Scrap Quantity, Rework Quantity, and Unit of Measure. You can prepopulate these fields with values. The system then adopts these values for the confirmation.

    Note Note

    If one of the enterable fields is not actually to be ready to accept input or is to be hidden, you can specify this in transaction COISF. For more information, refer to the system documentation on COISF.

    End of the note.