 Planning Order Costs on Cost Centers Locate this document in the navigation structure

Use

Using integrated planning of internal orders between internal orders and cost centers, you can manually plan order costs for non-planning integrated orders on the receiver cost centers. You have the following options:

  • Primary order costs, profile SAP101 or SAPALL

Activity-independent

Activity-dependent

  • Secondary order costs, profile SAP104 or SAPALL

Activity-independent

Activity-dependent

 ( )

With secondary order cost planning, you can create planning records for each sender/receiver for one or for several settlement cost elements.

See also:

Executing Primary Order Cost Planning