This table is used if production or process orders are to be created in the SAP system.
Field |
Description |
Type |
Length |
---|---|---|---|
EXTAUFNR |
External order number |
char |
10 |
<FIELD> |
Field name of an order |
char |
10 |
<VALUE> |
Value of field <FIELD> for the order |
char |
50 |
The following fields are possible:
<FIELD> |
Description |
Type |
Length |
Required entry |
---|---|---|---|---|
MATNR |
Material key |
char |
18 |
Yes |
WERKS |
Plant key |
char |
4 |
Yes |
AUART |
Order type |
char |
4 |
Yes |
BDMNG |
Quantity of the material component necessary to produce the specified order quantity |
char |
14 |
Yes |
GSTRP |
Basic start date |
dats |
8 |
Yes or GLTRP corresponding to scheduling direction |
GSUZP |
Basic start date (time) |
tims |
6 |
|
GLTRP |
Basic finish date |
dats |
8 |
Yes or GSTRP corresponding to scheduling direction |
GLUZP |
End time of order |
tims |
6 |
|
VERID |
Key specifying the various production techniques that can be used to produce a material |
char |
4 |
|
KDAUF |
Sales order key |
char |
10 |
|
PLNNR PLNAL PLNTY GMEIN |
Key for task list group Group counter Task list type Unit of measurement for order |
char char char unit |
8 2 1 3 |
Use these fields if you want to create an order without a material. They cannot be used separately or with field MATNR |
KDPOS |
Number uniquely identifying an item within a sales order |
numc |
6 |
|
CY_SEQNR |
Sequence number for production order |
numc |
14 (int) |
|
ESTAT |
User status. Must be used together with either Set User Status or Revoke User Status. User status must be transferred in internal format (E number from table TJ30) |
char |
5 (int) |
|
METHOD |
Methods are functions that can be carried out for only one object. Example: scheduling orders Possible values: SetTechnicalComplete RevokeTechnicalCompletion Schedule Release SetUserStatus RevokeUserStatus |
char |
1 |
Note
After you create a production order, the system carries out scheduling.
You must enter the date and time in the specified format.
The scrap quantity is taken from the material master or bill of material.
In order to enable scheduling with times, the following scheduling types must be defined in Customizing (
:5 = Forward scheduling
6= Backward scheduling