Calculation of Requirement Fluctuations 
If you have set the Consideration of Requirement Fluctuations indicator in the calculation profile , the system calculates the requirement fluctuations for a material and takes the calculated value into account as an additional buffer. To calculate the requirement fluctuations, the standard deviation of the smoothed requirement quantity is determined.
( )
The calculation of the requirement fluctuations delivers meaningful results only if you use an even distribution per period as the smoothing type. It does not make any sense to smooth requirements using a distribution key.
You have created a calculation profile in Customizing for Kanban under Automatic Kanban Calculation and Scheduling → Define Calculation Profiles and have set the Requirement Fluctuations indicator there
You have entered the calculation profile in the control cycle.
The requirement fluctuation is calculated as the standard deviation of the requirement quantity from the average requirement quantity per day. The average quantity is dependent on the smoothing type set. If you have not specified a smoothing type in the calculation profile, the average quantity is is calculated for the entire period of examination.
If you have set smoothing within a period of, say, a week, the quantity per week is calculated and the average per workday calculated from this.
The system displays the calculated quantity or calculated number of kanbans needed due to the requirement fluctuations in the Number of Kanbans Due to Requirement Fluctuations or Quantity Due to Requirement Fluctuations field of the transaction Check Proposal (PK08N)
You have set Smoothing Within a Week in the calculation profile.
Week 1 |
Monday |
Tuesday |
Wednesday |
Thursday |
Friday |
Requirements |
3 |
4 |
10 |
7 |
1 |
Average requirement per day |
5 |
5 |
5 |
5 |
5 |
Week 2 |
Monday |
Tuesday |
Wednesday |
Thursday |
Friday |
Requirements |
7 |
3 |
3 |
1 |
26 |
Average requirement per day |
8 |
8 |
8 |
8 |
8 |
The requirement fluctuation per day in week 1 is calculated as follows:

The requirement fluctuation per day in week 2 is calculated as follows: