 Rework Operations and Rework Quantities Locate this document in the navigation structure

Use

Rework Operations

An operation is marked as a rework operation by its control key .

Note Note

It is not possible to carry out an automatic goods receipt for operations that are marked as rework operations.

End of the note.

If an operation is marked as a rework operation, this has an effect on the operation quantity.

Rework Quantity

The following applies to the rework quantity:

  • If, when carrying out a confirmation, a rework order is created (see Trigger Points ), the confirmed rework quantity is taken over as the rework-order quantity.

  • If, when carrying out a confirmation, a reference operation set is inserted (via Trigger Points ), the confirmed rework quantity is taken over as the operation quantity of the inserted operations.

  • In the case of rework operations, you can maintain the operation quantity in the production order.

  • The operation quantity of a rework operation is not taken into account when scheduling calculates scrap-adjusted quantities for the operations in an order.

  • Any change in the order quantity has no effect on the quantity of the rework operation.