 Activating Availability Control Locate this document in the navigation structure

Use

In the budget profile, you use Activation Type to define whether, and how, availability control is to be activated.

Features

There are three different activation types:

  • 0 = Cannot be activated

If you chose background activation, you can activate Online Availability Control for a specific project.

Activities

When availability control is activated, the system does the following:

  • Determination of WBS elements carrying budget ("controlling elements")

  • Determination of associated assigned funds.

    It checks the assigned funds against the controlling element budgets. The assigned funds can be on the budget-carrying WBS element, the lower-level WBS elements and their assigned project orders.

After activation, each posting to the project is checked by the availability control.

Note Note

As availability control affects system performance, you should activate it in the background for projects with less detail, only when you think that the budget may be exceeded.

End of the note.