Earned Standards Plug-In 
You use this activity to view the scheduling standards and to view, claim or unclaim earned standards for an SFC number or a specific operation for an SFC number (see Earned Standards).
You can use this feature during the following processes:
Multiple operators work on the same SFC number at the same operation and each operator needs to claim standards for individual contributions
Tracking of operation partial completion for performance tracking and reporting purposes when operations have long processing times
Tracking of SFC number partial completion for performance tracking and reporting purposes, such as progress payments
You have setup the planned production standards for shop floor processes in Scheduling Standards Maintenance (see Scheduling Standards Maintenance).
You have set up the AWARD_UNCLAIMED_STDS hook point activity to award all unclaimed standards (see Award Unclaimed Standards).
The following table describes rules and settings that you can change for this activity in Activity Maintenance:
Rule |
Description |
|---|---|
AUTO_AWARD_SETUP |
YES: If any runtime standards are claimed, then all unclaimed setup standards are automatically awarded by the system. NO (default): The claiming of runtime standards does not automatically award unclaimed setup standards. |
AUTHORIZED_PERFORM_UNCLAIM |
If set to TRUE, allows the user of this activity to perform the Unclaim action |
PLUGIN_URL |
Specifies the plug-in location in the SAP ME folder structure Default value: /COM/SAP/ME/SCHEDULINGSTANDARDS/CLIENT/EARNEDSTANDARDSVIEWER.JSP |
The following table describes fields requiring explanation:
Field |
Description |
|---|---|
Action Type |
Allows you to select the Claim or Unclaim action |
Data Entry Mode |
Time Mode: Allows you to enter a new claim in time units Percent Mode: Allows you to enter a new claim as a percentage of the scheduling standards time |
Setup |
Standard: Setup time defined for the material or operation/step in Scheduling Standards Maintenance, in the specified time units Earned: The sum of setup claimed time and awarded time, in the specified units Earned %: Setup earned time expressed as a percentage of setup standard time Claim/Unclaim: The number of additional setup standards (expressed per the time unit or percent) requested to be claimed or unclaimed. Must be a positive number greater than zero. For unclaim, must be less than or equal to the standards earned. |
Run |
Standard: Runtime calculated from values for the material or operation/step in Scheduling Standards Maintenance, in the specified time units Earned: The sum of run claimed time and awarded time, in the specified units Claim/Unclaim: The number of additional run standards (expressed per time unit or percent) requested to be claimed/unclaimed. Must be a positive number greater than zero. For unclaim, must be less than or equal to the standards earned. |
Total |
Standard: The sum of the setup standard time and therun standard time, in whichever time unit is smaller Earned: The sum of the setup earned time and the run earned time, in whichever unit of time is smaller Earned %: Total earned time expressed as a percentage of total standard time |
Claim/Unclaim |
Allows you to save the entered changes to earned standards |
When you use the Change Production feature to change the routing or material for an SFC number, the system attempts to move the standards accordingly. For more information, see Earned Standards.