Show TOC

 Access Pegged Requirements Locate this document in the navigation structure

  1. In the MRP menu, choose   Evaluations   Pegged Requirements   .

    Note Note

    You can access the pegged requirements directly from the MRP list or the stock/requirements list , by positioning the cursor on the required MRP element and choosing  ( ) ( Pegged Requirements for Element ).

    End of the note.
  2. Enter the number of the MRP element (and the item number if it is a purchase requisition, purchase order or schedule line) and choose  ( ) ( Continue ).

    You now branch to the pegged requirements screen.

    Note Note

    As of SAP ECC 5.00 , the pegged requirements are displayed in the SAP List Viewer(ALV). (The system uses an ALV grid control.)

    You can also use a "classic“ list display (in the SAP List Tree). Choose   System   User Profile   Own Data   . On the Parameters tab page, set the parameter value of the parameter MD09_NO_ALV ( Pegged Requirement: No ALV Grid ) to X.

    End of the note.
  3. The following processing options are available:

    Function

    To Call the Function

    What you should know

    Display order route

    Position the cursor on the requirement and choose  ( ) Order route .

    The system displays the exact route from the requirement displayed to the MRP element over all BOM levels. The system displays a list of all the source MRP elements.

    Access stock/requirements list for material of pegged requirement

    Position the cursor on the requirement and choose  ( )   Details and Additional Functions and then Current Requirements/Stock List

    Display and change MRP element

    Position the cursor on the requirement and choose  ( ) ( Display Element ) or  ( ) ( Change Element ).

    Convert MRP element

    Choose  ( ) Details and Additional Functions and then Planned Order -> Production Order or Purchase Requisition -> Purchase Order .

    Access material memo

    Choose  ( ) ( Material Memo ).

    Access graphic

    Choose  ( ) ( Graphic ).

    A network graphic appears in a separate window. You can shrink or enlarge the graphic, access screens for processing individual MRP elements, print the graphic and so on.

    Print pegged requirements

    Choose  ( ) ( Print ).