Access Pegged Requirements 
In the MRP menu, choose .
Note
You can access the pegged requirements
directly from the MRP list or the stock/requirements list
, by positioning the cursor on the required MRP element and choosing
( )
(
Pegged Requirements for Element
).
Enter the number of the MRP element (and the item number if it is a purchase requisition, purchase order or schedule line) and choose
( )
(
Continue
).
You now branch to the pegged requirements screen.
Note
As of SAP ECC 5.00 , the pegged requirements are displayed in the SAP List Viewer(ALV). (The system uses an ALV grid control.)
You can also use a "classic“ list display (in the SAP List Tree). Choose . On the Parameters tab page, set the parameter value of the parameter MD09_NO_ALV ( Pegged Requirement: No ALV Grid ) to X.
The following processing options are available:
Function |
To Call the Function |
What you should know |
|---|---|---|
Display order route |
Position the cursor on the requirement and choose
|
The system displays the exact route from the requirement displayed to the MRP element over all BOM levels. The system displays a list of all the source MRP elements. |
Access stock/requirements list for material of pegged requirement |
Position the cursor on the requirement and choose
|
|
Display and change MRP element |
Position the cursor on the requirement and choose
|
|
Convert MRP element |
Choose
|
|
Access material memo |
Choose
|
|
Access graphic |
Choose
|
A network graphic appears in a separate window. You can shrink or enlarge the graphic, access screens for processing individual MRP elements, print the graphic and so on. |
Print pegged requirements |
Choose
|