Resource Setup 
You use this activity to change the setup state for a time-based resource and specify which material, shop order, or tool is loaded on the resource. For more information, see Time-Based Genealogy
The following table describes fields requiring explanation:
Field |
Description |
|---|---|
Setup State |
Current setup state of the resource: Breaking Down: Prevents work from being started at the resource, and indicates that the setup process for this resource is being reversed. For example, reels of components are being removed. Not Setup: Prevents work from being started at the resource, and indicates that the resource is not set up and is not in the process of being set up. Open: Allows work to be started at the resource, and indicates that the resource does not require to be set up. Setting Up: Prevents work from being started at the resource, and indicates that the resource is in the process of being set up. Set Up: Allows work to be started at the resource, and indicates that the resource is set up and ready for production. |
Setup Type |
Allows you to associate the resource with one or more materials, tool numbers, or a shop order |