Show TOC

Background documentationAdjust Production Start Time Locate this document in the navigation structure

 

You use the ADJUST_PROD_START hook point activity to correct the operator’s productive time by adjusting the start time by a fixed amount. This allows you to account for delays in sending the start message from an automated production machine.

This activity is used with the PRE_START hook point.

Rules

You have set the following rule for this activity in Activity Maintenance:

Rule

Setting

LOAD_TIME_PER_SFC

Specifies the adjustment to the loading time per SFC number in seconds