Start of Content Area

Procedure documentation Creating a PRT as a Material  Locate the document in its SAP Library structure

...

       1.      In the SAP menu choose Logistics ProductionMaster Data Production Resources and Tools, then Production Resources/ToolsMaterialCreate General.

If the production resource/tool (PRT) is not to be used immediately but from a particular date in the future, choose Material Create Schedule

       2.      Enter the relevant data on the initial screen.

You must enter a material type for which you can process the Prod. resources/tools view. Material type FHMI is defined for this purpose in the standard system.

       3.      Choose Enter.

The Select View(s) dialog box appears.

       4.      Select the Production Resources/Tools view and the views for any other areas in which the PRT is to be used. Choose Continue.

The Organizational Levels dialog box appears

       5.      Enter the plant, that you want to assign the PRT to, and if necessary organizational levels and profiles for the other views

If you have entered a material to copy from on the initial screen, also enter the organizational levels from which data is to be copied.

       6.      Choose Continue.

The first view appears.

       7.      Enter the necessary data and then choose Enter.

       8.      Repeat step 6 until you have edited all the views.

Note

You use the MM/PP status to release the material for use as a PRT.

You cannot change the base unit of measure or the unit of issue once you have assigned the material to operations as a PRT.

       9.      Save the material.

See also:

SAP Library Material Master (LO-MD-MM), in particular Creating Material Master Records and Changing Material Master Records

 

 

End of Content Area