Completion Confirmations
(CS-SE-CON/PM-WOC-JC)
You use the Completion Confirmations (PM-WOC-JC) component to document the status of the processing of a service or maintenance order.
As soon as an order has been released and the work is begun, the employees involved can enter completion confirmations in the system.
The Completion Confirmations (PM-WOC-JC) component is integrated with the following SAP components for different functions:
Function |
Integration with the Application Component |
· Confirmation of Material Used |
Inventory Management (MM-IM) |
· Confirmation of external services and external material |
Purchasing (MM-PUR) Invoice Verification (MM-IV) |
· Confirmation of Services |
Services (MM-SRV) |
· Entry of General Data on Attendance and Absence · Entry of Time and Additional Data in Time Management · Time collation |
Time Management (PT) |
The Completion Confirmation (PM-WOC-JC) component provides the following functions:
· Time Completion Confirmation
· Confirmation of Material Used
· Confirmation of Measurement and Counter Readings
· Completion confirmation of installation and dismantling information
· Technical Completion Confirmation
· Confirmation of External Services or External Material
· Cancellation of completion confirmation
· Display of Completion Confirmations
· Processing of Incorrect Completion Confirmations
· Cost Determination and Display of Actual Costs
· Decoupling of Completion Confirmation Processes