Setting Up Activity Hooks
You can use activity hooks in the system to automatically perform validation tasks or look up values during the manufacturing process (see Hook Point Activity and Hook Points).
You can set up activity hooks in the following activities:
Site Maintenance
Operation Maintenance
Routing Maintenance
Resource Maintenance
NC Code Maintenance
On the Activity Hooks
tab page, add one or more hook point activities by inserting new rows in the table.
Enter the following data:
Column |
Description |
|---|---|
|
The order the system executes this hook point. The system also uses this value to sequence all activities associated with this hook point (see Sequencing Object-Level Hook Points). |
|
Specifies when the system should execute the activity identified in the |
|
The hook point activity The system runs this activity when this hook point is triggered at the assigned object. |
|
Selected: Runs the specified activity when this hook point is triggered for this object Deselected: Disables the activity hook, for example when you are troubleshooting a problem |
|
Used only with hook point activities; contains additional parameters or values to be passed to the activity during the hook execution |
Save your entries.