Creating Simultaneous Group with Dependent StepsFill out the fields on the Main
tab page in Routing Maintenance
to describe the routing and specify its characteristics.
On the Routing
tab page, do one of the following:
If you cleared the Tabular Routing
checkbox on the Main
tab page, drag a Simultaneous Group
operation onto the drawing area and then drag the operations you want to include in the group onto
the Simultaneous Group
. Double-click the step to open its Properties
screen, and assign successors to the appropriate routing steps. Choose OK
.
If you chose the Tabular Routing
checkbox on the Main
tab, choose Insert New
as required for creating table rows representing the operation you want to include in the Simultaneous
Group
. For each operation in the group, choose Simultaneous
in the Step Type
field.
Fill out remaining necessary fields.
Save your entries.
For more information about routings, see Routing Maintenance.