Show TOC

 Budget Distribution Locate this document in the navigation structure

Use

Budget distribution in the Budget Control System (BCS) is based on the multi-level budget structure.

It is a specific http://aiokeh.wdf.sap.corp:50000/SAPIKS2/contentShow.sap?_CLASS=IWB_EXTHLP&TMP_IWB_TASK=PREVIEW&_LOIO=85DDCB5E078FC647BFB08861412B4662&_SLOIO=AB17F53B9F150248E10000000A11402F&RELEASE=6955&LANGUAGE=EN&_SEQNUM=57&_SCLASS=IWB_STRUCTbudget process in the http://aiokeh.wdf.sap.corp:50000/SAPIKS2/contentShow.sap?_CLASS=IWB_EXTHLP&TMP_IWB_TASK=PREVIEW&_LOIO=B51FF53BA41D2109E10000000A11402F&_SLOIO=AB17F53B9F150248E10000000A11402F&RELEASE=6955&LANGUAGE=EN&_SEQNUM=57&_SCLASS=IWB_STRUCTBudgeting Workbench which you can use to distribute budget from a higher to a lower node within your defined multi-level budget structure.

Depending on the settings you have employed in the IMG activity http://aiokeh.wdf.sap.corp:50000/SAPIKS2/content_get.sap?TMP_IWB_TASK=PREVIEW2&_CLASS=IWB_EXTHLP&_LOIO=441EB2F186A20889E10000000A422035&LANGUAGE=EN&RELEASE=6955Define Hierarchy Settings for Budget Structure , each node of the MBS is represented by a combination of FMAA elements which have been assigned the role "Multi-Level" (example: combination of funds centre and commitment item).

Prerequisites

The following prerequisites apply to the use of budget distribution:

You have created and activated Multi-Level Budget Structure

You have defined a multi-level budget structure and have generated nodes in that structure.

For information on the above points, read the relevant documentation .

If required, you have defined rollup scenarios in Customizing activity Define Document Types under Public Sector Management -> Funds Management -> Budget Control System (BCS) -> Budgeting -> Budget Entry ->Budget Entry Documents -> Document Definition

With rollup for processes such as Enter (that is Distribution, Transfer, Balance Entry, Revenues Increasing the Budget, Transfer with Cover Groups , and Carry Over ) , you can enter amounts in the lower account assignment of the hierarchy and the distribution from the top node to the lower level account assignment is generated automatically by the system. The rollup scenario of the document type must be set as Rollup with additive budget or Rollup without additive budget

The generation of additional lines for the processes Revenues Increasng the Budget (RIB) and Transfer with Cover Groups (Cover Eligibility) are somewhat different to the others in that:

Additional lines for RIB are generated using balanced entry ( BALS BALT ) and additional lines for transfer with cover groups are generated using normal transfer ( SEND RECV ).

Example

In the following structure,

A

|A1

|A11

|A111

Rollup with additive for Enter would work as follows:

A111 ENTR 10

A111 ENTR -10 (Balance of original line)

A111 DISR 10 (Distribution receiver)

A11 DISS -10 (Distribution sender)

A11 DISR 10 (Distribution receiver)

A1 DISS -10 (Distribution sender)

A1 DISR 10 (Distribution receiver)

A DISS -10 (Distribution sender)

A ENTR 10 (Rollup with additive)

All lines below the first one are generated automatically.

  • If required, you have defined distribution checks in Customizing activity Execute Distribution Checks for Process under Public Sector Management -> Funds Management -> Budget Control System (BCS) -> Budgeting -> Basic Settings -> Definition of Budget Data -> Distribution of Budget

You have set the distribution scenario for the document type as Active in Define Document Types . When this is active, the system will automatically generate the intermediate lines between sender and receiver when you distribute budget in the hierarchy using process Distribution. In this Customizing activity, you have three options for using rollup with distribution, that is:

No Rollup, in which case (distributing 10 from A1 to A111):

A1 DISS -10

A111 DISR 10

Rollup without Additive, in which case:

*A1 DISS -10

A1 DISS 10 (Balance of original line)

A1 DISR 10 (Distribution receiver)

A DISS -10 (Distribution sender)

*A111 DISR 10

A11 DISS -10 (Distribution sender)

A11 DISR 10 (Distribution receiver)

A1 DISS 10 (Balance of original line)

A1 DISR 10 (Distribution receiver)

A DISS -10 (Distribution sender)

(All lines other than those marked * are generated automatically)

Rollup with additive, in which case:

*A1 DISS -10

A1 DISS 10 (Balance of original line)

A1 DISR 10 (Distribution receiver)

A DISS -10 (Distribution sender)

A DISS 10 (Rollup with additive)

*A111 DISR 10

A11 DISS -10 (Distribution sender)

A11 DISR 10 (Distribution receiver)

A1 DISS 10 (Balance of original line)

A1 DISR 10 (Distribution receiver)

A DISS -10 (Distribution sender)

A DISS 10 (Rollup with additive)

(All lines other than those marked * are generated automatically)

This graphic is explained in the accompanying text.

Note that the rollup is not supported for use with statistical value type.

Procedure

Proceed as follows:

Go to the Public Sector Management part of Customizing and choose Funds Management Government ® Budget Control System ( BCS ) ® Budgeting ® Basic Settings ® Definition of Budget Data ® Budget Distribution ® Execute Distribution Checks for Process

In the Easy Access menu, access the Budgeting Workbench by choosing Accounting   ® Public Sector Management ® Funds Management ® Budgeting ® Budget Control System (BCS) ®   Entry Documents   ® Budgeting Workbench and activate distribution there.

Enter a sender and its relevant receivers in the Budgeting Workbench either manually or using the mass selection tool in menu Extras ® Select Master Data

Save the document.

See also

Reducing Budget Distributions