Adjust Production End Time
You use the ADJUST_PROD_COMPLETE
hook point activity to correct the operator’s productive time by adjusting the complete time by a fixed amount. As a result, you can account for delays in sending the complete message from an automated production machine.
This activity is used with the PRE_COMPLETE
hook point.
The following table describes rules and settings that you can change for this activity in Activity Maintenance
:
Rule | Setting |
|---|---|
| Specifies the adjustment to the unloading time per SFC number in seconds |