Park Budget 
You can park data for all budget types, original budget, supplements, returns, releases, and transfers.
The procedure for this is the same as the one used for entering and distributing original budget. For all budget types, you can enter a value date , after which the parked budget can be transferred to the current budget or, in the case of releases, to the budget already released. To do this, the parked budget must have been approved in the workflow. If you do not enter a value date, the parked budget will be copied to the current budget as soon as it is approved.
Example
Entered on: 01.10.1998
Value date: 01.12.1998
Approved on |
Budget is available on |
|---|---|
01.11.1998 |
Value date: 01.12.1998 |
01.01.1999 |
01.01.1999 |
To park budget, go to the in the menu, choose the required budget type, then
Post parked budget
The workflow administrator can manually post parked budget that could not be posted automatically in the workflow.
Cancel parked budget
The workflow administrator can manually cancel parked budget that has been rejected in the workflow but could not be canceled by the workflow initiator.
Note
Note that you cannot manually post or cancel documents while they are in the workflow.