You have already approved an engineering change request or have converted it to an engineering change order. However, you need to add or delete an object management record, or change the system status of an object management record.
...
1. Change the system status of the engineering change request or order as shown in the table.
The engineering change request/order is |
If you want to change an object management record, proceed as follows |
Approved |
Set the system status of the engineering change request to Withdraw approval. |
Converted |
Set the system status of the engineering change order to Order incomplete. |
ECO complete |
|
ECR complete |
You can no longer change any object management records. |
Released |
|
2. Process the object management records.
3. Reset the system status of the engineering change request or order to what it was originally.