Use
If changes have already been made to objects, you can no longer change the valid-from date. In this case, you must use the Shift date function.
The system checks the control data settings in Customizing.
See also:
Protected Time PeriodProcedure
If you want to shift the valid-from date, proceed as follows:
You see the Shift date dialog box.
Confirm this message and cancel the date shift function.
If the date shift causes a warning or error message to be displayed, the system generates a temporary log for all the BOMs and task lists concerned. This log lists all the change objects that do not allow the valid-from date to be shifted.
Check the effectivity periods of the change objects as required.