Conceptual documentation Protected Time Period  Locate the document in its SAP Library structure

In Customizing for Engineering Change Management, under Set up control data, you can define a time frame for additional date checks in the Date shift dataset. You define a protected time period that is checked in the following processing situations:

For this date check, you can specify whether a warning message or an error message is displayed when you try to perform these functions within the protected time period.

For example, you can specify that changes in the past are not allowed. Process flows for Materials Requirements Planning (MRP) may be relevant to the change. If materials have to be replaced by new materials, the replenishment lead time must be taken into account when you change the BOM.

Calculating the Protected Time Period

The baseline date for the check is the current date. The system calculates the warning or error time (in calendar days) either forwards or backwrds in time from the current date. The protected time period covers the key date calculated and all dates before this date.

You can process objects in this time period but you receive a warning message to remind you that the change objects need checking.

You are not allowed to process objects in this time period.

Note

If you enter a negative value (for example, 10-), the system calculates the protected time period from the current date backwards.

Example: Calculating the Protected Time Period (Warning)

Suppose you want to perform a date shift on the valid-from date of a change master record. The following settings are defined in Customizing:

Customizing

System Checks

Date check: active

Current date: 10.10.97

Warning time: 10 calendar days

Protected time period: 10.20.97 and the days before it

If you attempt to shift the valid-from date of your change master record to October 15, 1997, a warning message appears because October 15, 1997 is in the protected time period. If you confirm the warning message, you can shift the date to October 15, 1997.

Note

If you have an Error time in days of 10 days instead, the earliest date you can shift the valid-from date to is October 21, 1997.